Successful Week!

This week we had a successful week working on the house!  On Saturday we were able to complete the installation of the floor trusses, the access framing for the crawl space, the end blocking, and the rim boards. Linworth UMC provided an excellent lunch for the 8 volunteersthat enjoyed the cool fall weather.

Weather permitting, we hopefully we will install the floor decking Wednesday and seal it. The walls won’t be far behind. 

Please let Bonnie know by Tuesday morning if you can work on Wednesday, and by Thursday morning if you can work on Saturday.  Don’t forget to bring your own lunch if working on Wednesday.  Lunch will be provided on Saturday.

Bonnie can be reached at stbrendanhabitat@gmail.com.