Yesterday (Saturday) we raised two gable house trusses, raised the 25 trusses between them and put temporary bracing in place. See http://www.hilliardhabitat.org/Fair for some photos from the day.
We plan to work on Wednesday and Saturday again this week. Plans include porch construction, sub-fascia, garage preparation for truss installation, and install blue insulation board. All volunteers of varying skill levels are welcome!!!
Please let Bonnie know by Tuesday morning if you can work on Wednesday, and by Thursday morning if you can work on Saturday. Don’t forget to bring your own lunch if working on Wednesday. Lunch will be provided on Saturday.
Thank you!